The FAST Consortium, led

by FCC, recognised as the

Global Tunnelling Team of

the Year for its work on

the Riyadh Metro

FCC Construcción has completed the boring of the

Bolaños tunnels (Verín-Ourense). The works entail the

execution of two parallel single-track tunnels, each 6.7

kilometres long, on the Madrid-Galicia High-Speed Line.

FCC Construcción completes boring of the Bolaños

tunnel on

the Madrid-Galicia high-speed line

Briefs

Construction

The FAST Consortium, led by FCC, has

been recognised as the Best Global Tunne-

lling Team of the Year at the 2016 New Civil

Engineer Tunnelling Awards. Following the

successful completion of the excavation

work on the Yellow, Green and Purple lines

of the Riyadh Metro, the Consortium also

came in as runners-up in the Community

Engagement and Global Best Project of the

Year (above $500m) categories.

The winners were announced at an event

held at the Grosvenor House Hotel on Park

Lane in London on Thursday, 8 December.

The panel of judges highlighted the size

and diversity of the FAST excavation team,

made up of 9,500 people from 42 countries

who speak 22 different languages.

With an average excavation performance of 19.40 linear metres

per day in the first tunnel, the work took 11.5 months to comple-

te. The boring of the second tunnel saw an average excavation

performance of 24.32 linear metres per day, resulting in a com-

pletion term of 9.5 months. Therefore, there was a two month

reduction with regards to the time invested in the first tunnel.