Table of Contents Table of Contents
Previous Page  67 / 70 Next Page
Information
Show Menu
Previous Page 67 / 70 Next Page
Page Background

Antonio Franca,

Project Implementation

Director APM Terminals

Antonio Franca is the implementation direc-

tor of the Callao Port Project. He has been

working for APM Terminals since 2007,

although it was not until 2012 that he joined

the project shortly after the work began on

the remodelling, enlargement, and upgra-

ding of the Puerto de Callao project being

executed by the FCC-JJC consortium.

Tell us about your work.

As the project manager, I am in charge of

supervising the project and its objectives in

accordance with the provisions of the Con-

cession Agreement, providing the physical

assets to bolster the overall capabilities of

Callao Port.

How did the project come up?

The Port of Callao was built between 1930

and 1060. At that time, it was an impressive

infrastructure but 70 years later, it had rea-

ched the limit of its useful life.

After bidding for the Concession of the Port

of Callao, North Pier in 2011, APM Termi-

nal won the concession for the operations

of the North Terminal for a 30-year period.

One of the obligations contemplated in the

Concession Agreement was the develop-

ment and preparation of the port infrastruc-

ture for the next 50 years.

The development plan pursuant to the

Concession Agreement contemplates the

development of fie phases in which, the

two first phases will be completed in the

first quarter of 2016.

In Phase 1, 560 metres of new pier walls

were built, new buildings, a new access

was built, with 4 STS cranes (downloading

at the pier) and 12 cranes, jointly with other

equipment. Phase 2 calls for the develo-

pment of a multi-purpose 278 metre long

pier for bulk loads with a transporter sys-

tem.

Objectives of the project?

Improve the level of service by buil-

ding new pier walls and storage areas

and by acquiring state-of-the-art

equipment.

Build an infrastructure that is prepared

to handle the expected growth and

development of Peru over the next

50 years where the FCC-JJC Consor-

tium is playing an important role.

Improve the operational processes: we

have increase the movement of con-

tainers twofold, from 800,000 to 1.5

million tons.

Build and operate, which implies mi-

nimising the interruptions in current

operations as well as the construction

activities.

What have been the main challenges?

The main challenge in a project of this na-

ture is the fact that the construction work

is being carried out simultaneously as the

current operations. This, without any dou-

bt, is a work involving coordination and lo-

gistics to ensure that the different tasks are

executed on time, minimising the impact on

current operations.

How would you rate, as the client, the

work executed by the consortium, spe-

cifically by FCC?

The Consortium did a good job and execu-

ted the work successfully. The project did

not begin as had been expected; we faced

some challenges in the mobilisation period.

Nevertheless, we can assert that the initial

problems were overcome week by week.

We recognise the efforts made to complete

the project successfully.

Thanks to the good collaboration and

coordination, the Consortium was able to

minimise the impact on current operations

and that is something for which we are very

grateful.

FCC contributes experience, technical

knowledge, engineering solutions; it is clo-

se to and interrelates with the communities,

respects people and is committed to local

development.

Furthermore, its contribution in Occupatio-

nal Safety and Health has been very impor-

tant, reaching excellent safety standards at

the project. I believe that FCC has the best

team for the project, living up to the expec-

tations, challenges, and requirements.

In the image, Fernando Herrera and Antonio

Franca.