Table of Contents Table of Contents
Previous Page  63 / 70 Next Page
Information
Show Menu
Previous Page 63 / 70 Next Page
Page Background

The upgrading work also includes the

construction of an administration building

(five floors plus a rooftop terrace), a public

office building (two floors), a maintenance

workshop, and other minor projects.

One of the first deliveries required by the

client was completed in Pier 5 since the

client had purchased cranes to lift con-

tainers in China and it was necessary for

part of the pier to be completed in order to

install this equipment. FCC fulfilled its com-

mitment and, when the cargo arrived, the

new platform was ready for its installation.

The port project will upgrade the infrastruc-

tures to adapt them to the current demands

Progress achieved

in the project

Pi er 11 .

280 metres long,

completed. Delivered as part

of milestone 4 on 14 February

2015. Taken over on 24 May

and started operations on the

26th of the same month.

Buildings

Administrative and public building

was completed and delivered to the

client on 28 April 2015.

Other buildings: (Workshop, Ame-

nity, already completed).

Pavement

The new access areas and enlarge-

ment of the container park are already

completed after paving 157,000 m

2

.

Pier 5.

First milestone completed

on 28 August 2014 with the first 186

metres of Pier 5 to make it possible for

the client (APMTC) to download and

the STS Super Post Panamax cranes

with a reach of 68 metres, equivalent

to 23 lines of containers, in order to

be able to receive the largest ships in

the world, and transfer 18,000 twenty

feet containers. On 15 March 2015,

another important milestone was re-

ached by completing up to 360 ml.

Of the pier which made it possible to

continue with the pier’s operations

on the arrival of large ships. The full

560 ml. were finally completed in July

2015.

of the cargo transport system and to pro-

vide it with improved performance equip-

ment in line with the different types of cargo

handled at the port. Work on the 206 million

dollar project began in 2013 and a subs-

tantial completion of the project was achie-

ved on 18 December when it obtained the

“Sectional Completion Milestone 5” taking

over certificate.

The traffic capacity

of the port will be one

million containers

per year