On Monday, 14 September, the ICA- FCC-

MECO consortium started to fill the new ac-

cess channel that will be connecting Corte

Culebra with the third set of locks in the

Pacific sector as part of the fourth phase

of the dry excavation project of the Pacific

Access Channel of the Panama Canal en-

largement project.

New FCC Bulletin

in Central America

The latest issue of the Central American

Bulletin is now available. It includes reports

on the progress achieved in projects, cor-

porate social responsibility, and training

at FCC Construcción Panama and Costa

Rica.

For further information

Read the Bulletin

The new channel measures 6.1 kilome-

tres in length and is 218 metres wide. The

bottom of the excavation is 9.14 metres

above sea level.

The ICA-FCC-MECO consortium is execu-

ting this project which includes the excava-

tion of 26 million cubic metres, a large part

of this in rock formations, and the construc-

tion the Borinquen 1E 2.4 kilometre long

loose material dam.