Several measures were implemented
that have made it possible to elimina-
te most of the pumping stations all of
which has resulted in energy savings.
A new 75,000 m
3
deposit was introdu-
ced which will enable the city of Lleida
to have a back-up supply equivalent to
two and a half days of consumption.
The water and sanitation network was
digitalised in the Aqualia’s corporate
Geographic Information System (GIS)
known as Aqualiagis) and the mathe-
matic modelling of the supply network
was executed.
Water pressure throughout the city
has been improved by meshing the
networks and eliminated unnecessary
pressure regulation systems.
Master Plan
An ambitious water supply Master Plan
was launched in 2008 and is expected to
be completed by 2023. The Plan contem-
plates all the actions to be carried out in re-
lation to water supply over these 15 years,
such as segmentation, increasing telecon-